Contingency plan
Contingency plans are plans than could be enacted to mitigate project risks identified during risk assessment, if those risks increase or materialise. That is, they are alternative courses of action devised to cope with project risks.
Predictable risks that could be mitigated with forward planning might include:
- Non-delivery of materials. An alternative design might be prepared, or bulk or specific items could be pre-ordered before contractors are appointed
- Lack of available work force. This could be tackled by the provision of a site labour camp or by overseas recruitment.
- Lack of plant and equipment availability (or plant failure or access to spare parts). Plant such as piling rigs and spares could be ordered during the design stages prior to contractor involvement.
- Illness. This could be mitigated by insurance cover for key personnel.
- The risk of obtaining planning permission or other statutory approvals. This might be mitigated by early consultation with statutory authorities prior to design, or by employing ex-statutory authority employees, or consultants familiar with the statutory authority.
- Information and communications technology failure. This might be mitigated by duplicating facilities, establishing back-up procedures and providing uninterrupted power supplies.
- Failure of power or water supply. This might be mitigated by the duplication of supply, uninterrupted power supplies or the provision of standby generators.
NB Functional Standards Common Glossary, published by the Cabinet Office, defines contingency planning/ plans as: ‘A course of action and resulting document(s) that prepares the organisation to respond effectively to future significant events, incidents and risks.’
[edit] Related articles on Designing Buildings
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.